Silverstrand is reporting strong progress on the Elimbah East project, delivering the vital civil, mechanical, and electrical infrastructure needed to support the region’s long-term growth.

The community project encompasses approximately 5.5 kilometres of new sewer rising mains, a sewer pump station, emergency storage facilities, and advanced odour control systems designed to service the expanding Elimbah community at Moreton Bay.

Construction activity across the site is moving swiftly:

  • Pipeline & Tunnelling: Crews have successfully completed four micro-tunnel bores and installed roughly 1,200 metres of dual sewer rising main. As pipeline sections are finished, restoration work follows closely behind to return surrounding areas to normal.
  • Pump Station & Barometric Loop: Major concrete pours for the primary structures and maintenance holes are now complete. Work is actively focused on the valve chamber, flow meter pit, air valve pit, and remaining maintenance holes.
  • Equipment & Procurement: With the procurement of major mechanical, electrical, and process equipment fully wrapped up, the project is well-positioned to move into its next phase of construction and testing.

It is a great team effort as Silverstrand continues to deliver critical wastewater infrastructure to support growth across the Elimbah community.