Australian Projects
Silverstrand prides itself on delivering quality projects, safely, on time and within budget. Innovative solutions, engineering ingenuity, adherence to the highest safety and quality standards and professional construction management are the hallmarks of Silverstrand.
Silverstrand have a proven track record and have displayed on previous projects the ability to operate and overcome obstacles in challenging environments whilst maintaining high standards to the satisfaction of our clients.
Moorabool North Wind Farm
Client: |
Zenviron |
Location: |
Ballan, Vic, Aus |
Duration: |
6 Months |
Scope: |
Construction of 50no. structural concrete wind turbine foundations and concrete works for 2 new electrical substations |
Logan Enhancement Project
Client: |
CPB Contractors |
Location: |
Logan, Qld, Aus |
Duration: |
18 Months |
Scope: |
Construction of 3 new multi span bridges, 2 new cut and cover tunnel structures, bridge widening works and various concrete works |
Kingsford Smith Drive Upgrade
Client: |
Lend Lease |
Location: |
Hamilton, Qld, Aus |
Duration: |
16 Months |
Scope: |
Construction of in-situ stormwater and sewer pits, load transfer concrete slabs and marine outlet structure |
Sideling Creek Dam Upgrade
Client: |
Fulton Hogan |
Location: |
Petrie, Qld, Aus |
Duration: |
6 Months |
Scope: |
Upgrade of existing dam spillway and downstream plunge pool works |
Gold Coast Light Rail Stage 2
Client: |
CPB Contractors |
Location: |
Gold Coast, Qld, Aus |
Duration: |
14 Months |
Scope: |
FRP Concrete Works and Civil Works |
Transcity Legacy Way
Client: |
Transcity J.V. |
Location: |
Brisbane, Qld, Aus |
Duration: |
6 Months |
Scope: |
Construction of Western Ventilation Building, Cut and Cover Tunnel and Air Monitoring Facility |
APLNG Condabri Water Treatment Facility
Client: |
CPB Contractors/ APLNG |
Location: |
Miles, Qld, Aus |
Duration: |
22 Months |
Scope: |
FRP Concrete Works, Rock Protection, Grouting & Pipework Installation to a new CSG Water Treatment Plant |
Duncan Rd Drainage Upgrade
Client: |
Roadtek |
Location: |
Sheldon, Qld, Aus |
Duration: |
6 weeks |
Scope: |
Construction of new storm water drainage, pits, kerb and channel |
East Nogoa Waste Water Treatment Plant
Client: |
Monadelphous |
Location: |
Emerald, Qld, Aus |
Duration: |
8 Months |
Scope: |
FRP Concrete works to a new Water Treatment Plant |
Warrego Highway Culvert Rehabilitation
Client: |
Roadtek |
Location: |
Karalee, Qld, Aus |
Duration: |
1 Month |
Scope: |
Rehabilitation of existing corrugated iron culvert |
Rubyanna Waste Water Treatment Plant
Client: |
Downer Utilities |
Location: |
Bundaberg, Qld, Aus |
Duration: |
9 Months |
Scope: |
FRP Concrete works to a new Water Treatment Plant |
Gaza Rd Abutment Protection Works
Client: |
Roadtek |
Location: |
Mt Gravatt, Qld, Aus |
Duration: |
2 Months |
Scope: |
Earthworks and shotcrete to bridge abutment |
QCLNG Northern Water Treatment Plant
Client: |
Laing O’Rourke/ QCLNG |
Location: |
Wandoan, Qld, Aus |
Duration: |
9 Months |
Scope: |
FRP Concrete Works to a new CSG Water Treatment Plant |
APLNG Gas Gathering Discharge Pipeline
Client: |
CPB/ APLNG |
Location: |
Reedy Creek & Condabri, Qld, Aus |
Duration: |
2 Months |
Scope: |
Construction of DN750 RCP Pipeline, pit and headwall |
APLNG Wet Well
Client: |
CPB/ APLNG |
Location: |
Condabri, Qld, Aus |
Duration: |
2 Months |
Scope: |
Installation of 3.6m dia Pre-Cast Wet Well |
Cooroy to Curra Early Works
Client: |
BMD |
Location: |
Gympie, Qld, Aus |
Duration: |
2 Months |
Scope: |
Construction of Drainage Pits, Barrier End Terminals, V Drains and Spoon Drains |
Warrego Highway Culvert Construction
Client: |
Roadtek/ DTMR |
Location: |
Brassall, Qld, Aus |
Duration: |
2 Months |
Scope: |
Construction of Various RCP and RCBC Culverts |
Runner A & B Barbers Creek Flood Regulators
Client: |
Fulton Hogan |
Location: |
Barham, NSW, Aus |
Duration: |
4 Months |
Scope: |
Construction of Concrete Flood Regulators |
Burton Coal Mine Culvert
Client: |
Thiess Mining |
Location: |
Moranbah, Qld, Aus |
Duration: |
3 Months |
Scope: |
Construction of 800m long Culvert, Spillways and Rip Rap |
Gladstone Sea Wall Culvert
Client: |
Abigroup |
Location: |
Gladstone, Qld, Aus |
Duration: |
3 Months |
Scope: |
Construction of a Sea Wall Culvert |
DTMR Median Infill and Bikeway Construction
Client: |
Lend Lease |
Location: |
Brisbane, Qld, Aus |
Duration: |
3 Months |
Scope: |
Construction of new Concrete Medians, Kerbing and New Bikeways |
BCC Bus Stops
Client: |
Roadtek/ TMR |
Location: |
Brisbane, Qld, Aus |
Duration: |
2 Months |
Scope: |
Upgrade of existing Bus Stops |
GLNG Fairview Hub 4
Client: |
Clough-Downer JV |
Location: |
Fairview, Qld, Aus |
Duration: |
20 Months |
Scope: |
Labour & Plant Hire |
Roy Hill Port Non-Process Infrastructure
Client: |
DECMIL |
Location: |
Port Headland, WA, Aus |
Duration: |
3 Months |
Scope: |
Construction of Port Warehouse Buildings |
Rockhampton Shed Development
Client: |
Queensland Steel Products |
Location: |
Rockhampton, Qld, Aus |
Duration: |
5 Months |
Scope: |
Construction of Multiple Warehouses and pavements |
Woorabinda Water Reservoir
Client: |
Dept. of Local Govt. |
Location: |
Woorabinda, Qld, Aus |
Duration: |
3 Months |
Scope: |
Construction of 750Kl Concrete Reservoir |
Browns Plains Car Park Construction
Client: |
Ernst & Young |
Location: |
Browns Plains, Qld, Aus |
Duration: |
2 Months |
Scope: |
Construction of a new Car Park and Civil Works |
Woodlands to Veales Rd RSS Wall Construction
Client: |
Thiess |
Location: |
Townsville, Qld, Aus |
Duration: |
2 Months |
Scope: |
Construction of an RSS Wall |
Ermington Boardwalk Construction
Client: |
Steelworks Engineering |
Location: |
Ermington, NSW, Aus |
Duration: |
4 Months |
Scope: |
Construction of new timber and steel boardwalk |
Wall Revetment Construction
Client: |
Tweed Shire Council |
Location: |
Chinderah, NSW, Aus |
Duration: |
2 Months |
Scope: |
Excavation and construction of new Revetment Wall |
Bollingbrooke Feeder Station
Client: |
Civil Team Engineering |
Location: |
Mackay, Qld, Aus |
Duration: |
3 Months |
Scope: |
Excavation, installation and backfilling of electrical condutis |